Playbooks error
-
13/جمادى الثانية/1433 09:20 م
Hello,
I'm having the a problem with connecting Playbook to PWA instance. In my case I have two PWA instances running in the same server, let's say:
1. http://server/pwa
2. http://server:1979/pwa
Both running just fine.
Running playbooks from the server I can connect to instance 1 but not to instance 2 I got the error "Invalid PWA instance, username and/or password"
Any idea on why playbooks does not connect to the second instance, is it because the port?The second instance was created by using a full attach PS 2007 dbs, but again, the instance runs just fine
Thanks for any helpDaniel Villacis
جميع الردود
-
13/جمادى الثانية/1433 11:06 م
-
13/جمادى الثانية/1433 11:23 م
-
14/جمادى الثانية/1433 12:44 ص
I'm running Playbooks directly from the server, so no problems with firewall.
Maybe is because the second instance was created using ps 2007 dbs? Did you reproduce this scenario as well?
Thanks!!
Daniel Villacis
-
14/جمادى الثانية/1433 04:44 ص
yes, I am able to connect using upgraded 2007 PWA databases using same port.
check your DNS seeting for the second URL
For a quick test, by updating AAM setting with the help of hosts file
Hrishi Deshpande – DeltaBahn Senior Consultant
Blog | < | LinkedIn- تم التحرير بواسطة Hrishi.Deshpande 14/جمادى الثانية/1433 04:45 ص correction