Team Resource in PWA 2010 : error "Impossible to reassign"
-
03/جمادى الثانية/1433 08:28 ص
Hello,
I created a Team resource in Project Server 2010 and assigned this resource on a task in a specific project.
A member of that team goes to his Tasks page, Insert Row / Insert Team Task, select the task and click Assign to me.
The system throws the error message: "Impossible to reassign one or several specified tasks. This may happen when the proposed resource to assignment is already assigned on the task, or when the specified assignment has been deleted or denied."
I'm sure that the individual resource is not already assigned on that task: I created it right now on purpose.
So what could be the issue?
Thanks
جميع الردود
-
03/جمادى الثانية/1433 08:57 ص
Hi
I think you should refer to the matching post:
Team assigments in 2010 - why can't i get it working?
or
Delay when assigning team resource to myself
Manish
- تم التحرير بواسطة Manish M Upadhyay 03/جمادى الثانية/1433 09:01 ص
- تم وضع علامة كإجابة بواسطة WLID1966 03/جمادى الثانية/1433 03:16 م
-
03/جمادى الثانية/1433 03:17 م
OK, the user has to be in the project team...