MDX code for Cumulative Work in EPM Cube
-
15. května 2012 13:59
Hi
Does anyone know how or have a sample of how to add a 'Cumulative Work' field in the EPM 2010 portfolio analyzer cube?
Any samples would be greatly appreciated.
Thanks
Všechny reakce
-
16. května 2012 5:45
Hi there--
Cumulative Work for a tasks is calculated based on work already performed on the task + scheduled remaining work on the task.
These values are based on the task Work field and added to the previous time period for the cumulative value. For each time period, cumulative work equals cumulative work for the previous period + scheduled work for this period.Please see the below example:
http://carl-projectserver.blogspot.in/2011/06/return-of-data-geek-epm-olap-cube.htmlThis example would give you a cumulative WORK calculation, specifically from the earliest date possible.
> sum(periodstodate([time].[(all)]),[measures].[Work])Some more samples:
http://www.msprojectnow.com/Blog/tabid/142/entryid/11/Default.aspxHope that helps.
If you found this post helpful, Please "Vote as Helpful";. If it answered your question, Please "Mark as Answer".
Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82- Upravený Amit Khare - Project Management Consultant 16. května 2012 5:46