MS Project 2010 - How to add Custom date formats
-
29. dubna 2012 6:48
Is there a way to add Custom Date formats in MS Project?
e.g. I need to display date as mmm-yyyy (Feb-2012). The available list does not include such a format.
Regards,
Manoj
Všechny reakce
-
29. dubna 2012 17:12
It is not possible to apply a customized date display format to Project in application level.
We can display date values of any field in another custom field using a formula. For example, the following formula in Text1 field displays Start dates in mmm-yyyy format: Format( [Start], "mmm-yyyy")
Regards.
- Navržen jako odpověď Manish M Upadhyay 30. dubna 2012 8:46
- Označen jako odpověď Julie SheetsMVP, Moderator 2. května 2012 20:17
-
29. dubna 2012 21:20Moderátor
Technically date formats can be changed, but only by changing the date format under Windows' control panel and regional settings. Since you can't anticipate what other PC's settings will be, Project User's suggestion of using a custom Text field is the better option.Rod Gill
The one and only Project VBA Book
Rod Gill Project Management
- Navržen jako odpověď Rod Gill MVPMVP, Moderator 29. dubna 2012 21:21
- Označen jako odpověď Julie SheetsMVP, Moderator 2. května 2012 20:17