MS Project 2010 - How to add Custom date formats
-
29. april 2012 06:48
Is there a way to add Custom Date formats in MS Project?
e.g. I need to display date as mmm-yyyy (Feb-2012). The available list does not include such a format.
Regards,
Manoj
Alle besvarelser
-
29. april 2012 17:12
It is not possible to apply a customized date display format to Project in application level.
We can display date values of any field in another custom field using a formula. For example, the following formula in Text1 field displays Start dates in mmm-yyyy format: Format( [Start], "mmm-yyyy")
Regards.
- Foreslået som svar af Manish M Upadhyay 30. april 2012 08:46
- Markeret som svar af Julie SheetsMVP, Moderator 2. maj 2012 20:17
-
29. april 2012 21:20Redaktør
Technically date formats can be changed, but only by changing the date format under Windows' control panel and regional settings. Since you can't anticipate what other PC's settings will be, Project User's suggestion of using a custom Text field is the better option.Rod Gill
The one and only Project VBA Book
Rod Gill Project Management
- Foreslået som svar af Rod Gill MVPMVP, Moderator 29. april 2012 21:21
- Markeret som svar af Julie SheetsMVP, Moderator 2. maj 2012 20:17