  • Donnerstag, 19. November 2009 21:54
     
     
    Hello

    In Project 2010 beta I can't seem to find the PERT analysis features. There is a PERT add in references but I can't see how to start this or how to access PERT data fields, or PERT views. Any advice would be appreciated.

    Thanks

    Lars

Alle Antworten

  • Sonntag, 22. November 2009 15:10
    Moderator
     
     
    Hello Lars,

    I don't believe the PERT analysis feature is in Project 2010.  If you have installed Project 2010 Beta to a machine where there are other versions of Project (2007, 2003) the add-in you are seeing may be from those versions.

    On a clean install (no previous versions of Project), I do not see the PERT add-in reference.

    I hope this helps.

    Julie
  • Dienstag, 1. Dezember 2009 15:51
     
     Beantwortet
    Hello Lars

    The PERT is no more part of the 2010 but there seems to be a Workaround here : http://blogs.technet.com/projectified/archive/2009/11/24/3296207.aspx

    Regards