Answered Status date in Timeline View

  • Freitag, 15. Januar 2010 09:47
     
     
    Is it possible to show "status date" when working with timeline view?

Alle Antworten

  • Freitag, 15. Januar 2010 16:06
    Moderator
     
     Beantwortet
    Hi Winson,

    Welcome to this Microsoft Project newsgroup :) As far as I know, there's no built-in way to do this. However, you could create a milestone (called it Status Date?)and show it on the Timeline. Double click on it and enter the Status Date you want. As Status Date defaults to 1700, I suggest you show the times as well on the timeline so you can synchronise the times.

    FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

    Hope this helps - please let us know how you get on :)

    Mike Glen
    MS Project MVP
    See http://tinyurl.com/2xbhc for my free Project Tutorials