Open file name macro
-
Montag, 23. April 2012 15:49
Hi,
This is my 1st attempt at using macros with project 2010 so please be patient with me for asking possibly a simple question!!!
I have tried to create a macro that passes 1 table & 1 field from the global mpt to an open project file then save & close. I wanted this so i could add a new custom column with lookup field to all my project files ( around 180 of them ). This seemed to be simple task until i needed to find the vba code for adding opened file name to the macro as highligthed below in red text.
I hope my question makes sense, can anyone advise please?
Sub Macro2()
' Macro Macro2
' Macro Recorded Mon 23/04/12 by Steve Hartwell.
OrganizerMoveItem Type:=1, FileName:="Global.MPT", ToFileName:="Project1", Name:="TRW Gantt"
OrganizerMoveItem Type:=9, FileName:="Global.MPT", ToFileName:="Project1", Name:="Project File Owner (Text9)"
ViewApply Name:="Gantt Chart"
FileSaveAs Name:="D:\SharedProjects\TRW Base Files\Project1.mpp", FormatID:="MSProject.MPP"
FileCloseEx
End Sub
Regards
Steve
Alle Antworten
-
Montag, 23. April 2012 15:55
Steve.
The current active file name is:
Activeproject.Name
John
- Als Antwort markiert Steve TRW Montag, 23. April 2012 16:00
-
Montag, 23. April 2012 16:02
Thanks John,
To push my question to the next level would it be possible to program the macro to open all files in a particular folder and run the same macro on them automatically? Where would i find out how to do this on the net?
Regards
Steve
-
Montag, 23. April 2012 16:06
John,
I have added the code as below but it hasnt worked, what did i do wrong?
Regards
Steve
Sub Steve_Macro1()
' Macro Steve_Macro1
' Macro Recorded Mon 23/04/12 by Steve Hartwell.
OrganizerMoveItem Type:=1, FileName:="Global.MPT", ToFileName:="Activeproject.Name", Name:="TRW Gantt"
OrganizerMoveItem Type:=9, FileName:="Global.MPT", ToFileName:="Activeproject.Name", Name:="Project File Owner (Text9)"
ViewApply Name:="Gantt Chart"
FileSave
FileCloseEx
End Sub
-
Montag, 23. April 2012 16:07Moderator
take the quotes off of Activeproject.nameBrian Kennemer - Project MVP
DeltaBahn Senior Architect
endlessly obsessing about Project Server…so that you don’t have to.
Blog | Twitter | LinkedIn- Als Antwort markiert Steve TRW Montag, 23. April 2012 16:10
-
Montag, 23. April 2012 16:10
brian,
Thankyou that works. easy when you know how eh!
Steve
-
Montag, 23. April 2012 16:14Moderator
Yes it is possible but I dont have the code available i front of me right now.
This code will not open all the files in a folder but it will loop through all the projects you currently have open.
So you would manually open the projects into Pro all at once or in groups and then run the macro.
Try it on some TEST PROJECTS.
Notice that instead of Activeproject.name I changed it to P.Name and put all the code in a loop where P is a project. the loop grabs all the open projects and makes P equal one of them. The code does it's thing and then moves to the next one.
Sub AllOpen() Dim P As Project For Each P In Application.Projects OrganizerMoveItem Type:=1, FileName:="Global.MPT", ToFileName:=P.Name, Name:="TRW Gantt" OrganizerMoveItem Type:=9, FileName:="Global.MPT", ToFileName:=P.Name, Name:="Project File Owner (Text9)" ViewApply Name:="Gantt Chart" FileSave FileCloseEx Next P End SubBrian Kennemer - Project MVP
DeltaBahn Senior Architect
endlessly obsessing about Project Server…so that you don’t have to.
Blog | Twitter | LinkedIn- Als Antwort markiert Steve TRW Montag, 23. April 2012 16:50
-
Montag, 23. April 2012 16:57
Brian,
Thanks, i have tried both, they both only seem to work on new blank projects not existing projects? Also it does not seem to be closing the files after saving?
I get the following (obviously the file name in the error is different for each file i try) error on all projects other than new blank ones.
Run-time error '1101':
The file "PR18616" was not found
regards
steve
Does the macro look for the file name or a name within the open file its self? wondering if i have made some sort of school boy error in the creation of the files i wish to change -
Montag, 23. April 2012 17:34Moderator
OK not sure why it is doing that but Im seeing some odd behavior as well. So instead of that loop try this one, which is actually what you wanted to start with.
Change the C:\Foo\ to your directory where your MPP files are located. Then run the macro.
Sub x() Dim strFilename As String Dim strPath As String Dim P As Project Application.ScreenUpdating = False strPath = "C:\Foo\" strFilename = Dir(strPath & "*.mpp") Do While Len(strFilename) > 0 Application.FileOpenEx (strPath & strFilename) Set P = Application.ActiveProject OrganizerMoveItem Type:=1, FileName:="Global.MPT", ToFileName:=P.Name, Name:="TRW Gantt" OrganizerMoveItem Type:=9, FileName:="Global.MPT", ToFileName:=P.Name, Name:="Project File Owner (Text9)" FileClose pjSave strFilename = Dir Loop Application.ScreenUpdating = True End SubBrian Kennemer - Project MVP
DeltaBahn Senior Architect
endlessly obsessing about Project Server…so that you don’t have to.
Blog | Twitter | LinkedIn -
Montag, 23. April 2012 18:03
Brian,
Thats fantastic thanks. However i still have the same error
Run-time error '1101':
The file "project1" was not found
I just created 3 or 4 blank projects entered them into a test folder and added that folder destination to the macro. It obviously found the folder and opened the 1st file but not sure why it says file was not found
Regards
Steve
- Bearbeitet Steve TRW Montag, 23. April 2012 18:05 spelling!!
-
Montag, 23. April 2012 18:12Moderator
-
Montag, 23. April 2012 18:17
Brian,
Yes I just made some blank projects to test project1, project2 etc etc etc. I used the code as you entered above and edited just the filepath.
Thanks
Sub x()
Dim strFilename As String
Dim strPath As String
Dim P As Project
Application.ScreenUpdating = False
strPath = "C:\files to dopy and paste\"
strFilename = Dir(strPath & "*.mpp")
Do While Len(strFilename) > 0
Application.FileOpenEx (strPath & strFilename)
Set P = Application.ActiveProject
OrganizerMoveItem Type:=1, FileName:="Global.MPT", ToFileName:=P.Name, Name:="TRW Gantt"
OrganizerMoveItem Type:=9, FileName:="Global.MPT", ToFileName:=P.Name, Name:="Project File Owner (Text9)"FileClose pjSave
strFilename = Dir
Loop
Application.ScreenUpdating = True
End Sub -
Montag, 23. April 2012 18:23Moderator
I dont know what to say. This code runs perfectly on my machine.
I have three projects in my folder: Project1.mpp, foo.mpp, foo2.mpp
I run the code and it copies a table called Table1 into those projects, saves and closes them. (I have this line in my code rather than your TRW Gantt: OrganizerMoveItem Type:=1, FileName:="Global.MPT", ToFileName:=P.Name, Name:="Table 1")
What if you close all open projects before you run the code?
Brian Kennemer - Project MVP
DeltaBahn Senior Architect
endlessly obsessing about Project Server…so that you don’t have to.
Blog | Twitter | LinkedIn -
Montag, 23. April 2012 20:36
Noooooooooooooooooooo, so close i can taste the success!!!
You dont suppose its anything to do with my OS do you i am running windows 7 ? This has caused us some user issues on other functions compared with XP.
Scrap that i have tried both- Bearbeitet Steve TRW Montag, 23. April 2012 20:40
-
Dienstag, 24. April 2012 07:47
Brian,
My hunch was correct after all, i have just passed the macro and files to a collegues computer who is running xp pro and it works fine so i guess its a windows 7 issue AGAIN!
If i made a new post on here do you think i may get an answer?
Steve