Help to understand Microsoft project task duration
-
Mittwoch, 20. Januar 2010 17:52
Hi guys,
Could anyone let me know the factor where is have
Duration
-customizing training 41.93 dys
define course evaluation 32 dys
How come it is not 32 dys, but instead 41.93 dys in customizing training? Cos define course evalation is the subgroup of customizing training.
Pls help
Regards,
Calvin<input id="gwProxy" type="hidden"><!-- Session data--></input> <input id="jsProxy" onclick="jsCall();" type="hidden" />
Alle Antworten
-
Mittwoch, 20. Januar 2010 19:29Moderator
Hi Cyber3Cat,
First, Sorry, this is not a 2010 question as this may be normal behaviour for all versions of Project.
If the subtask is somehow interrupted (say split) the split depos not count in its duration.
But it sdoes coiunt in the duration of the summary task which spans from the start of the first subtask till the end of the last one, whether there are interruptions or not.
Hope this helps,
Jan- Als Antwort vorgeschlagen Julie SheetsMVP, Moderator Donnerstag, 21. Januar 2010 20:59
-
Donnerstag, 28. Januar 2010 06:12Hello Cyber3Cat,
Check the values in your Options / Schedule
Day is 8 hours
Week is 40 hours
For example, if your day is 7 hours in your Options/ Schedule and you put 8 hours in for work, the duration will show up as fractions.
Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA
www.WhartonComputer.com -
Freitag, 29. Januar 2010 04:25
Hello Cyber3Cat,
Actually, I was a little sleepy the night before. To prevent the fractions, make sure the the Options/Schedule hours match your Project Calendar that is being used.
Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA
www.WhartonComputer.com- Als Antwort markiert Cyber3cat Mittwoch, 10. Februar 2010 03:03
-
Mittwoch, 10. Februar 2010 03:04Thanks alot guys. :)