Where in the published database are the baseline 'saved-on' dates
-
Tuesday, 29 May 2012 6:14 PM
I'm using Project Server 2007. I want to query the published database for the dates baseline 1, 2, and 3 were set via Project Professional. I know I can get this data if I open the plan, go to Tools --> Tracking --> Set baseline (in the drop-down I can see the date the baseline was saved). But where in the published database is this date stored?
Dave Shultz, PMP
All Replies
-
Tuesday, 29 May 2012 8:38 PMModeratorUnfortunately not all data is copied to the reporting db.
Rod Gill
The one and only Project VBA Book
Rod Gill Project Management
-
Wednesday, 30 May 2012 5:08 AM
See if this helps you in getting what you are looking for:
Database reference - ProjectServer_Reporting
dbo.MSP_EpmTaskBaseline
Abhijeet M. Mohite ------------------------------------------------------------------------------------------------------------------------------------------If you found this post helpful, please "Vote as Helpful";. If it answered your question, Plase "Mark as Answer"
-
Wednesday, 30 May 2012 11:48 AMModerator
Just to point out if it helps....best practice is to always keep the latest baseline stored in Baseline0, then copy it with each change to Baseline1, 2, 3, etc. That way, all reports are always based off of Baseline0.
Not sure why you're looking to get the baseline save date - but if it's simply to identify the most recent baseline, then the above practice would also resolve the issue without the need for querying the Published database.
Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky
-
Friday, 1 June 2012 3:05 PM
Hi,
This query display Project Name, Duration, task baseline start date, task baseline finish date and task baseline created date
SELECT MSP_PROJECTS.PROJ_NAME, MSP_TASK_BASELINES.TB_BASE_NUM, MSP_TASK_BASELINES.TB_BASE_DUR,
MSP_TASK_BASELINES.TB_BASE_START, MSP_TASK_BASELINES.TB_BASE_FINISH, MSP_TASK_BASELINES.CREATED_DATE
FROM MSP_TASK_BASELINES INNER JOIN
MSP_PROJECTS ON MSP_TASK_BASELINES.PROJ_UID = MSP_PROJECTS.PROJ_UIDRegards.
MCTS, MCITP
- Proposed As Answer by Jalalblali Friday, 1 June 2012 3:05 PM
- Marked As Answer by Mike GlenModerator Tuesday, 17 July 2012 8:53 PM