Project 2010 Multi Select text box
-
Thursday, 7 June 2012 8:39 PM
Creating a custom text field with associated lookup values is a no brainer within MS Project 2010. Is there a way to create one that allows multiple selections from the lookup? I would expect it work just like any other multi-select drop down list.
All Replies
-
Thursday, 7 June 2012 9:45 PMModerator
Hello KMS01,
No, sorry. The only multi-value field in Project is the Resource Names field. All others are single value. A possible work around is to create multiple fields and allow people to select a value from more than one field.
I hope this helps.
Julie
- Proposed As Answer by Project User Friday, 8 June 2012 1:07 AM
- Marked As Answer by KMS01 Friday, 8 June 2012 4:22 PM
-
Friday, 8 June 2012 5:58 AMModerator
Hi KMS01,
In Standalone version of project its not possible, but in Project Server mode having enterprise custom field with multi-select is possible.
Sapna S
-
Friday, 8 June 2012 4:22 PM
Hi Julie,
Thanks for the reponse. Perhaps in the next release this feature can be worked in.
Ken