MS Project Professional 2010 and SharePoint 2010 Foundation - Project Tasks Synchronisation
-
Monday, 26 March 2012 12:43 PM
Synchronisation of MS Project 2010 (Prof. Edition) with SharePoint 2010 (foundation) Project Tasks list fails with the following message.. (No MS Project server in this environment).
Invalid Predecessor
SharePoint only supports Finish-to-Start predecessors without constraints or lag times. Modify the affected predecessor and sync. again.
I would like to know if there is any workaround for the above issue, without having to modify the Project plan as per the above message. Thanks
All Replies
-
Monday, 26 March 2012 4:16 PM
Removal of Predecessor field in SharePoint helped synchronisation for now.- Proposed As Answer by Anderson C. Oliveira Tuesday, 9 April 2013 12:42 PM
-
Tuesday, 3 April 2012 7:58 AMModerator
Hi svblr,
This feature works only for FS linkage as of now; you can refer to : http://blogs.msdn.com/b/project/archive/2009/10/19/project-2010-introducing-sync-to-sharepoint.aspx?PageIndex=2 also there is no Lag & Lead Support as of now.
Sapna S
- Marked As Answer by Sapna Shukla - Project MVPMVP, Moderator Saturday, 7 April 2012 4:36 AM
-
Friday, 13 April 2012 2:00 PMThanks Sapna. I would also like to know if it's possible for the resources to enter the time spent (in hrs on a week) on a task in SharePoint 2010, so this can be synched with MS Project 2010.
-
Friday, 13 April 2012 2:19 PMModeratorYes it is possible, synch is 2-way communication between MS Project & SharePoint Site; resource updates can be synched back to MS Project 2010. There is a full video on this at : http://www.microsoft.com/project/en-us/demos.aspx titled SharePoint 2010 and Project Professional 2010.
Sapna S