Answered Mocrosoft project 2010

  • Wednesday, 6 June 2012 6:39 PM
     
     

    When I open a MS project schedule 2010 version. make some changes and try to "SAVE AS" I get a error message telling me I have a schedule older that MS proejct 2003, which I do not.

    I found if I "SAVE" first then "SAVE AS" its sometimes OK.

    Any Idea what up or suggestions other than do the "SAVE" then "SAVE AS" and hope?

All Replies

  • Thursday, 7 June 2012 12:35 AM
     
     Answered

    John,

    First question. Was this plan originally created in an earlier version of Project?

    Second question. Do you have SP-1 installed for Project 2010? If not, you can get it at, http://technet.microsoft.com/en-us/office/ee748587.

    John