Project Server My Tasks or My Timesheet problem

Proposed Project Server My Tasks or My Timesheet problem

  • Wednesday, 11 January 2012 8:01 AM
     
     

    When clicking the notes icon next to the Task Name or the task name in the My tasks view an unexpected error occurs.  It happens to all the users in the company. It is set to the single entry mode. How can I fix this?

All Replies

  • Wednesday, 11 January 2012 12:19 PM
    Moderator
     
     
    What is the error, and do you get any errors in the ULS logs
    Ben Howard [MVP] blog | web
  • Friday, 13 January 2012 8:03 AM
     
     

    Hi Ben

    This is the feedback on the ULS logs:  'http://schemas.microsoft.com/office/project/server/webservices/PWA/SecurityCheckUserPagePermission'  - can you assist?

     

  • Friday, 13 January 2012 10:39 AM
    Moderator
     
     
    Hi, I cannot access that web site.
    Ben Howard [MVP] blog | web
  • Friday, 13 January 2012 11:15 AM
     
     

    Hi Ben

    The error is:  Error:  An unaxpected error has occured.  Troubleshoot issues with MicrosoftSharePointFoundation and then in the ULS logs is the above note.  It seems to me it is a user page permission - will that be Project Server or Internet issue?

  • Friday, 13 January 2012 11:58 AM
     
     
    Sorry for falling in the thred:

    Are you having the project server 2010 with SP1/June 2011 or later CU installed ?
    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
  • Friday, 13 January 2012 12:02 PM
     
     

    Yes it is installed

     

  • Saturday, 14 January 2012 4:33 AM
     
     

    Can you open the task and see the notes?

    Did you or some do a copy/paste into the notes?  If you did, this is your problem.  Sometimes when copying from WORD or EXCEL (or any application) and pasting into PWA or Project, the unprintable characters will cause problems.  Try deleting all the text in the NOTE and typing the text into the field.... SAVE and the PUBLISH..

    Do the problem still occur?

    Cheers!


    Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA
    www.WhartonComputer.com
  • Monday, 16 January 2012 6:49 AM
     
     

    Hi Michael

    Thanks for your feedback.  This was a brand new Project Server 2010 installation and configuration and the problem occur right from the start.  Nobody in the company can open the details on the tasks or the notes on the My Tasks page.  I have added the note field and users can type a note into the field.

    Kind regards

    Lettie

  • Monday, 16 January 2012 8:44 AM
     
     Proposed
    your My task web part is corrupted so you can re add my task web part.
    • Proposed As Answer by Maheshwar85 Monday, 16 January 2012 8:45 AM
    •  
  • Tuesday, 17 January 2012 6:07 AM
     
     

    Hu Nagesgwa85

    I will definately try this and let you know.  I will be at the client site next week.

    Thanks