Errors message for the Preview Update window in PWA
-
Monday, 17 October 2011 3:49 PM
Hi,
when I try to review status updates sent to me inside the Preview Update window in PWA, I get the following pop-up error:
The view failed to load. Press OK to reload this view with the default settings. Press Cancel to select another view.
I found the same post here http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/3ef48901-0d1a-47ef-b6e3-6d1eed64ba66?prof=required and the person replied that he
"Yes, I finally realised that if you got links on summary tasks the view doesn't load. I removed those links and the web-part appeared."
I edited the project plan in Project Pro and I didn't see any predecessors on summary tasks. Does anyone else know what can cause this issue?
Thanks
All Replies
-
Wednesday, 19 October 2011 5:48 AM
Hello!!!
Did you removed the assignments from the summary tasks?
Which version of the Project Server?
Try it...
-
Friday, 21 October 2011 9:23 PM
I'm using 2010 version.
I'm fairly new to the system. How would I remove assignments from the summary tasks?
Thanks for help
- Edited by pawel850 Friday, 21 October 2011 9:26 PM
-
Tuesday, 25 October 2011 3:59 PMI found the problem. One of the subtasks was linked to sumamry task. Thank you for help.