问题 Visual report

  • Saturday, 24 December 2011 4:00 PM
     
     

    Hi,

    Is there an option to generate visual report showing the baseline start and baseline finish of the tasks and the actual start and actual finish dates of tasks in ms project 2007.

    Also it would be helpful if you could highlight if this could be done for only the summary tasks rather than each individual task.

    Thanks in advance.

    Sarthak

All Replies

  • Sunday, 25 December 2011 10:56 AM
    Moderator
     
     

    Sarthak --

    No, it is not possible to generate a visual report showing the baseline start and baseline finish of the tasks and the actual start and actual finish dates of tasks in Microsoft Project 2007.  You use Visual Reports to generate totals for Work and Cost.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

  • Sunday, 25 December 2011 2:21 PM
     
     

    Dale,

    Thanks for your prompt reply. It definitely helps. I'l get back to you incase of further doubts.

    Thanks

    Sarthak

  • Tuesday, 27 December 2011 8:45 PM
    Moderator
     
     

    Sarthak --

    You are more than welcome for the help, my friend.  :)


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"