updating lookup table in Project detail page without clicking on server setting -->custom fields and lookup table

คำตอบ updating lookup table in Project detail page without clicking on server setting -->custom fields and lookup table

  • Wednesday, 6 June, 2012 11:09 AM
     
     

    Hi,

    In PWa site , while creating new project , there is one lookup field on PDP page, I need to modify this lookup field in such away that.

    Project  managers should be able to update the custom lookup table if the required value does not exist in lookup table.

    what exactly I need to do for this?.

    Regards,

    Swati

All Replies

  • Wednesday, 6 June, 2012 11:21 AM
     
     Answered

    Hi Swati,

    As a process, Project metadata custom fields/lookup table should be updated by Administrators or someone having permissions of "Manage Enterprise Custom Fields". If you want PM should be able to update the Lookup value if the value which is not there, It would require a custom deveopment on PDP page. In your customized PDP page, they can select any value such as "NA" & you have a text box which is mandatory once PM selects the "NA", the suggested value will be taken from text box & PSI -Lookuptable web services will be call to update the lookup table.

    Alternatively, You can have the UI to update the lookup table which PM can use if they don't see the desired value.

    I would suggest to setup the process instead of customized solution in this case. As it doesn't show major benefits.

    Hope that helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • Marked As Answer by MsSPJ Friday, 15 June, 2012 9:15 AM
    •