I want to know how to change working time in MS Project

Answered I want to know how to change working time in MS Project

  • Thursday, 12 August, 2010 10:37 AM
     
     

    I have MS Project 2010 Beta version, and I want to change "Standart Calendar" on "24 Hours", but when I click "Change Working Time" and then choose "24 Hours" and click "ok" it does not work. It stays the same Standart Calendar? Can you tell me what is the problem? Maybe here is some function to switch off?

    thank you

All Replies

  • Thursday, 12 August, 2010 11:03 AM
     
     Answered

    Hi Kakha,

    To apply Project Calender, Go to Project > Project Information, Click Calender option select 24 Hrs. and click OK

    that the porcess of applying calendar in MSP


    Regards, Sujit - MSTC
    • Marked As Answer by Kakha Dapqo Thursday, 12 August, 2010 11:07 AM
    •  
  • Thursday, 12 August, 2010 11:07 AM
     
     
    thank you very much ...
  • Thursday, 12 August, 2010 12:04 PM
    Moderator
     
     
    Kakha --
     
    In addition to changing the Project calendar in the Project Information dialog, you should also change the Non-Working Time calendar as well.  To do this, apply the Gantt Chart view and then zoom to the Days level of zoom.  Double-click anywhere in a gray shaded band for a weekend.  The system will open the Timescale dialog and pre-select the Non-Working Time tab.  On this tab, select your desired calendar and click the OK button.  When you set the Non-Working Time calendar, this applies your desired calendar to the display shown in the Gantt chart.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

  • Thursday, 12 August, 2010 1:22 PM
     
     
    yes, Thank you very muc, i have already done it.