Sunday, April 29, 2012 4:13 PM
Hi,
I developed a rapper to edit/save/submit timesheet actuals.
I can edit timesheet lines actual works and even comments via PSI In Tied Mode(SEM), every thing is ok But when we re create the timesheet all Comments will be null (actuals are OK).
Whats the forgotten trick?
Thanks a lot.
Aria Cop
All Replies
-
Monday, April 30, 2012 7:07 AM
Hi Aria Cop--
When you read the TS data, do you see the TS_Comm field as Null? Did you verifywhile updating the Timesheet the TS_Comments fields data is captured & new comments are added with the same?
Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
-
Monday, April 30, 2012 12:08 PMModeratorJust FYI that Projectum, a Danish company, markets and sells a solution thatdoes exactly that. (Site's in Danish, but you can translate with an onlinetranslator)http://www.projectum.dk/produkter/projectum®-timesheet-daily-comments.aspx
Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky -
Tuesday, May 08, 2012 10:39 AM
Hi Andrew
Unfortunately we have our owned Rapper UI and our staffs will not be able to enter their actuals via timesheet jsgrid because of some presence checking laws in our company.
Aria Cop
- Edited by Morteza Ghorbani Tuesday, May 08, 2012 11:00 AM
-
Tuesday, May 08, 2012 10:46 AM
Hi Amit,
we use reporting server views for faster performance, there is a column for daily actuals comments and it will filled when i save timesheet via psi, i can view them in msp_TimesheetActual_OlapView view.
but when i delete and then create my timesheet again (in tied mode) all actuals will be there again but comments will be lost.
I think i should update tasks comments via statusing webservice , i just use timesheet update and StatusingChangeRowLog.
thanks
Aria Cop
- Edited by Morteza Ghorbani Tuesday, May 08, 2012 10:56 AM