How to check document attach or not in pwa site

Unanswered How to check document attach or not in pwa site

  • Monday, April 16, 2012 6:33 AM
     
     

    Hi everyone,

    How to check document attach on not in project server-2010(pwa site).If document is not attach give a message or if attach also give a message  ....


    Neeraj



    • Edited by Neeraj149 Monday, April 16, 2012 6:40 AM
    •  

All Replies

  • Monday, April 16, 2012 8:12 PM
     
     

    Do you mean by project site? If yes, then when it should send you message?


    Thanks, Kashif

  • Tuesday, April 17, 2012 5:44 AM
     
     

    Hi Kashif,

    Thanks Replay..

    yes i am use project site and how to implement our Requirement............


    Neeraj


    • Edited by Neeraj149 Tuesday, April 17, 2012 5:45 AM
    •  
  • Tuesday, April 17, 2012 6:39 AM
     
     

    Neeraj, please state your problem clearly, so we can answer appropriately.


    Thanks, Kashif

  • Friday, April 27, 2012 11:02 AM
     
     

    Hi Neeraj

    To answer your question, first open the project center, select the required project, navigate to Project Site from here. SharePoint Project Site will open up in a new tab.

    Now in Quick Launch 'Project Document' is visible under 'Libraries'. Click on Project Document.

    From here, you can add a document to your project. As soon as you added the document, there will be a message "The document was successfully added". And document will be shown up in the list. Hence you will get to know that it was attached.

    --------------------------------------------------------------------------------------

    In PWA--> Project Center --> in Indicators Field the document icon will be visible. SO from here also you will get to know that it was attached.

    I hope, it cleared your doubt & please try to be more specific when you post some question so that you can get the responce quickly.

    Thanks.


    Manish