Textbox controlsource
-
Monday, April 23, 2012 1:31 PM
using ms project 2007 and 2010
is it possible to set the controlsource for a userform textbox to a cell in Excel?
example: tbMyvalue is a textbox in my user form. I want to assign its value to cell B1 in sheet1 from an Excel file.
seems like the controlsource should be something like: C:\mydata.xls, sheet1, B2
That doesn't work, but I can't seem to find anything meaningful regarding how to effectively use the controlsource property in a user form.
GMAN1941
- Moved by Sapna Shukla - Project MVPMVP, Moderator Monday, April 23, 2012 2:12 PM (From:Project Standard and Professional General Questions and Answers)
All Replies
-
Monday, April 23, 2012 4:17 PM
GMAN1941,
First you need to get the Excel application object. Then I usually declare an object identifying the specific workbook and worksheet. From there it is easy and convenient to address individual objects/properties of that worksheet object. It is also advisable to declare your variables. Your best resource is to use the Object Browser from the VB Editor window. Oh, and don't forget to set a reference to the Excel Object library under Tools/References.
Dim xl as Excel.Application
Dim s as Worksheet
Set xl = GetObject("C:\mydata.xls")
set s = xl.Workbooks([name]).Worksheets(1) 'where [name] is a string of the workbook name (e.g. "MyWorkbook")
s.Range("B2") = byMyvalue
Hope this helps.
John
-
Monday, April 23, 2012 6:18 PM
John,
Thanks for the input. I wanted to know how to properly enter the necessary string into the Controlsource field of the textbox in the user form. but maybe i don't need that. maybe i simply set the excel object and then the textbox:
tbMyvalue = s.range("b2")
GMAN1941
- Marked As Answer by GMAN1941 Tuesday, April 24, 2012 2:19 PM
-
Monday, April 23, 2012 9:31 PMModerator
John's right, you can't set a source. You could link to a custom field for a task, but that is risky. DDE Links are notorious for corrupting files. For John's code to work you need to add a reference in teh Editor to Excel, or use:Dim xl as Object Set xl = GetObject(,"Excel.Application") s.Range("B2") = xl.ActiveWorksheet.Range("B1").value set xl=nothingFor both versions the workbook needs to be open before the code is run, but you can change the code to open the file first provided the file's location is known.Rod Gill
The one and only Project VBA Book Rod Gill Project Management- Marked As Answer by GMAN1941 Tuesday, April 24, 2012 2:19 PM
-
Tuesday, April 24, 2012 2:57 PM
Rod,
thanks for the input. I have this part solved. as an add-on question, is it possible to address a field by is user name?
example:
Dim jtask as task
For Each jTask In ActiveSelection.Tasks
jtask.IPTMgr = "Jones" where IPTMgr is a user name for Text3
-
Tuesday, April 24, 2012 11:58 PM
GMAN1941,
Yes but not directly. Try the following syntax:
jtask.getfield(application.FieldNameToFieldConstant("IPTMgr")) = "jones"
John
-
Wednesday, April 25, 2012 1:20 PM
John,
exactly what i need - however, i tried: jtask.getfield(application.FieldNameToFieldConstant("IPTMgr")) = "jones"
and i get an error message:
"Function call in left-hand side of assignment must return variant or object"
the code is: (abreviated) - and where Text21 is defined as IPTMgr
dim Jtask as task
for each Jtask in Activeselection.Tasks
jtask.getfield(application.FieldNameToFieldConstant("IPTMgr")) = "jones"
next Jtask
am I missing something?
GMAN1941
-
Wednesday, April 25, 2012 2:50 PM
John,
disregard - i discovered the problem - the code should be "setfield" not "getfield"
GMAN1941
-
Wednesday, April 25, 2012 3:04 PM
GMAN1941,
Yeah, my bad. Try the following:
jtask.setfield fieldID:=application.FieldNameToFieldConstant("IPTMgr"), value:="joe"
John
-
Wednesday, April 25, 2012 6:33 PM
John,
actually, it's:
jtask.setfield fieldID:=application.FieldNameToFieldConstant("IPTMgr",pjTask), value:="joe"
and you can substitue "IPTMgr" and "joe" with variables
GMAN1941