Hello
We are using MS Project 2007 Professional and are doing Earned value on projects
Project A is almost complete with remaining work of 80 hours and the project actuals has overrun the Baseline so actuals are greater than what was baselined.
Our Baseline (BCWP) is 94,000 hours and the calcualtion of earned value (BCWP) is 95,000 which makes our SPI greater than 1.
Essentially the project is complete, we are just waiting on some approvals from the client so we haven't closed out 1 support task.
When the project is complete is it ok to have an earned value that from a totals hours perspective surpasses the baseline? and how?
Thanks