project 2010 task re ordering / drag drop not working
-
Tuesday, June 19, 2012 4:27 PM
hi - hoping someone can please help with the following issue.
i'm running project 2010 connecting to project server. I have just discovered I cannot re order / drag and drop tasks to different locations.
in project 2007 i achieve this by
> select a task by clicking on the id (entire task is highlighted) > hover the mouse pointer over the task until a cross arrow symbol appears > left click and drag to a new location > release left click > task has been moved to the new location
in project 2010 i cannot get the cross arrow symbol appear! does anyone have a suggestion to resolve
I've tried this in multiple views, including the built in gantt which uses the table named entry
thanks
paul
All Replies
-
Tuesday, June 19, 2012 4:40 PMModerator
Hi Paul,
Point to the row heading (ID Column) until a four-headed arrow appears, and then drag the task to where you want it in the Gantt Chart view.
Check if this option is Activated : File->Options->Advanced ->Edit Tab -> Check- Allow Cell Drag and Drop.
Sapna S
- Marked As Answer by pbyford Wednesday, June 20, 2012 8:11 AM
-
Tuesday, June 19, 2012 5:13 PMModerator
Paul --Please try the following:- Click File > Options.
- In the Project Options dialog, select the Advanced tab.
- In the Edit section, select the Allow Cell Drag and Drop checkbox.
- Click the OK button.
Please let us know if this resolves your problem with drag and drop.Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"- Marked As Answer by pbyford Wednesday, June 20, 2012 8:11 AM
-
Wednesday, June 20, 2012 8:14 AM
All,
Your suggestions have resolved my issue. I had to check Allow Cell Drag and Drop on the advanced tab options.
Thanks for your help
Paul
-
Wednesday, June 20, 2012 11:45 AMModeratorWelcome Paul for the feedback.
Sapna S