MS Project 2010 - How to add Custom date formats
-
Sunday, April 29, 2012 6:48 AM
Is there a way to add Custom Date formats in MS Project?
e.g. I need to display date as mmm-yyyy (Feb-2012). The available list does not include such a format.
Regards,
Manoj
All Replies
-
Sunday, April 29, 2012 5:12 PM
It is not possible to apply a customized date display format to Project in application level.
We can display date values of any field in another custom field using a formula. For example, the following formula in Text1 field displays Start dates in mmm-yyyy format: Format( [Start], "mmm-yyyy")
Regards.
- Proposed As Answer by Manish M Upadhyay Monday, April 30, 2012 8:46 AM
- Marked As Answer by Julie SheetsMVP, Moderator Wednesday, May 02, 2012 8:17 PM
-
Sunday, April 29, 2012 9:20 PMModerator
Technically date formats can be changed, but only by changing the date format under Windows' control panel and regional settings. Since you can't anticipate what other PC's settings will be, Project User's suggestion of using a custom Text field is the better option.Rod Gill
The one and only Project VBA Book
Rod Gill Project Management
- Proposed As Answer by Rod Gill MVPMVP, Moderator Sunday, April 29, 2012 9:21 PM
- Marked As Answer by Julie SheetsMVP, Moderator Wednesday, May 02, 2012 8:17 PM