MS Project Professional 2010 and SharePoint 2010 Foundation - Project Tasks Synchronisation

Answered MS Project Professional 2010 and SharePoint 2010 Foundation - Project Tasks Synchronisation

  • Monday, March 26, 2012 12:43 PM
     
     

    Synchronisation of MS Project 2010 (Prof. Edition) with SharePoint 2010 (foundation) Project Tasks list fails with the following message.. (No MS Project server in this environment).

    Invalid Predecessor

    SharePoint only supports Finish-to-Start predecessors without constraints or lag times. Modify the affected predecessor and sync. again.

    I would like to know if there is any workaround for the above issue, without having to modify the Project plan as per the above message. Thanks