Ignore Actual Date Unexpectedly in Excel File by Excel Import to Local Project
-
Thursday, December 10, 2009 3:27 AM
Hello,
Excel import cannot change actual start date and actual end date with following operations.
-1. Open local project (.mpp file created by Project Professional 2010) by Project Professional 2010.
-2. Save as file, type is excel format. (such as .xlsx or .xls)
-3. Set following options on Export Wizard.
Data Format : Selected Data
Map : New Map
Data Type : Task (only)
Microsoft Excel Option : Include Header
Map : (Excel Fields are default)
Unique ID
Task Name
Actual Start Date
Actual End Date
-4. Change / Set Actual Start Dates and Actual End Dates.
-5. Open excel file created at -3..
-6. Set Following options on Inport Wizard.
Map : New Map
Way of Import : Marge
Data Type : Task (only)
Microsoft Excel Option : Include Header
Map : (All are default)
Unique ID
Task Name
Actual Start Date
Actual End Date
-7. Actual Start Date and Actual End Date of all tasks are not changed, like no operation.
If I directly input Actual Start Date or Actual End Date, Actual Start Date or Actual End Date are changed input value.
But if I input by Import Wizard, Actual Start Date and Actual End Date are not changed, ignore values in excel file.
Why Import Wizard ignore values in excel file ?
Thanks,
MCITP(Database Developer/Database Administrator)
All Replies
-
Friday, January 08, 2010 6:25 PMModerator
Do the tasks in question have assignments and/or % complete defined? Are those values also being exported and then re-imported?- Marked As Answer by Gary Chefetz, MCITP, MCT, MVPModerator Tuesday, February 23, 2010 12:42 AM