How to tell if a resource is part of a resource pool
-
Monday, April 23, 2012 7:56 AM
Hi,
Is there a way identifiying resources that are not part of a resource pool and are in fact attached to a project file rather than the resource pool?
Regards
Steve
All Replies
-
Monday, April 23, 2012 8:10 AM
Hi Steve
In Resource Sheet View (where all resources are listed) only, there will be an indicator for a local resouce.
Local Resources are those resources who are not included in Resource Pool.
Ensure that you open MSP in connected mode.
Manish
- Edited by Manish M Upadhyay Monday, April 23, 2012 8:11 AM
- Proposed As Answer by Andrew Simpson Monday, April 23, 2012 8:19 AM
- Marked As Answer by Steve TRW Monday, April 23, 2012 9:58 AM
-
Monday, April 23, 2012 9:39 AMIn the Resource Sheet View, Entry Table, insert the "Project" column. It tells you where the resource lives.
- Marked As Answer by Steve TRW Monday, April 23, 2012 9:58 AM
- Unmarked As Answer by Jan De Messemaeker - Project MVPMVP, Moderator Monday, April 23, 2012 8:06 PM
-
Monday, April 23, 2012 9:58 AM
Manish,
Thank-you, its easy when you know how!!
Regards
Steve
-
Monday, April 23, 2012 9:59 AM
Trevor,
Thank-you also, very helpful reply
Regards
Steve
-
Monday, April 23, 2012 7:00 PMModerator
A Generic Resource is identified by the following symbol:
double heads, where one of it is faded.Local resource is a resource that is added to a project plan and not pulled from the Enterprise Resource Pool, will be displayed with
icon in Resource Sheet view.Enterprise Resource won't have any icon associated with it.
Sapna S
- Marked As Answer by Steve TRW Monday, April 23, 2012 8:32 PM
- Unmarked As Answer by Jan De Messemaeker - Project MVPMVP, Moderator Tuesday, April 24, 2012 8:04 AM
-
Monday, April 23, 2012 8:09 PMModerator
Hi Steve,
Funny, all the replies you got suppose you are running Project Server and an Enterprise resource pool - whereas from other posts I have the impression you aren't
Now for the bad news - if you aren't in a Server environment but just running a "nomal" resoruce pool... your question is impossible to solve because when a file is linked to a resoruce pool the latter picks up every resource form the sharer file! In fact, ther are no "local" resources; eveyone "resides" in the Pool!
So in this environment, when you show the Project column in any resoruce view, all resources will show the name of the resoruce pool, not the file where they "originated".
Greetings,
-
Monday, April 23, 2012 8:32 PMThanks, yes you are correct i am not in a server enviroment. Are you saying the resources on the project files are adopted by the resource pool, i.e. if the original file with a local resource was deleted would that resource be deleted also or would i now have that resource on the resource pool? I had previously had to run seven different global location plans using a copy of the same resource pool attached to each. I had made the assumption that when i attached all these files to a single resource pool they would link in no problem as the resource names are identical? I would have assumed i would have multiple resources of the same name if this was not true?
- Marked As Answer by Jan De Messemaeker - Project MVPMVP, Moderator Tuesday, April 24, 2012 8:05 AM
- Unmarked As Answer by Jan De Messemaeker - Project MVPMVP, Moderator Tuesday, April 24, 2012 8:05 AM