Unanswered PWA 2010 - The 'Publish' process hangs

  • Thursday, April 26, 2012 1:15 PM
     
     

    LS

    We use PWA to add members to a project team routinely.

    What is happening routinely now is that the publish step fails to complete successfully and the process gets stuck in the 'Save Job Queued' step.

    I open the project file in PWA 2010 - I select the Project tab - add team member - Save&Close

    this all works - then i click the task tab - click on publish - and now the process hangs in 'Save Job Queued'

    After a couple of minutes i get a pop-up that says - Operation Still processing - the save job has been queued but is taking longer than expected to process.

    Any clues? It works fine in MS Project 2010 - and may be related somehow to synching with the project site?

    Ideas welcome.

    TT

All Replies

  • Thursday, April 26, 2012 3:09 PM
     
     

    Hi there,

    Check the status of jobs by navigating to PWA>>Server Settings>>Manage Queue Jobs

    Add "Success" from Job Completion States  and refresh the status

    Also review Event Logs on Project Server and SQL server Logs on SQL server.


    Hrishi Deshpande – DeltaBahn Senior Consultant
    Blog | < | LinkedIn