Project Server 2010 - Can a project manager create and assign tasks outside a project ?

Answered Project Server 2010 - Can a project manager create and assign tasks outside a project ?

  • Monday, May 28, 2012 4:45 PM
     
     

    I know that the objective is to manage the project portfolio, but it is possible for a project manager to creat and assign isolated tasks  that don´t belong to a project ???

     A resource can add a personal task to his/her timesheet but does a project manager can assign it to him/her?

     

    Thks a lot!!

All Replies

  • Monday, May 28, 2012 7:53 PM
     
     Answered

    Hello Liliana,

    this is not possible. Tasks can only be created for projects.  Personal Tasks/Administrative Tasks can be added to a personal timesheet, but they do not appear anywhere else on the server. In particular, they are no projects, cannot be managed, do not appear in the usual reports, project centre views, etc.

    They can only be visualised in reports which particularly query timesheet data from within the Reporting DB or the Timesheet Cubes.

    Kind regards,
    Adrian

    • Marked As Answer by Liliana U Wednesday, May 30, 2012 10:38 PM
    •  
  • Wednesday, May 30, 2012 10:40 PM
     
     

    Thanks for the answere!!!!  :)