Timesheet ribbon calculating days incorrectly
-
Monday, April 23, 2012 2:36 PM
The timesheet status bar is calculating 1 day as 0.94.
The actual timesheet captures 1 day correctly. The default reporting units in Project Server is days and the number of hours in a standard timesheet day is 7.5. I'm not sure where else I need to check. Is this a known issue?
All Replies
-
Wednesday, April 25, 2012 2:33 PM
Hi Leah,
Do all users and projects use a standard calendar? another thing to check within the project in MSP what is the standard day and week in hours?
Will
-
Thursday, May 03, 2012 2:01 PM
Hi Will
We have two calendars, the project server standard calendar which we have changed to 7.5 hoursand a company specfic calendar which has 7.5 hours as standard. All our plans in MSP use the company specific calendar. Do you have any other ideas
Thanks for your help.
Leah
- Edited by Leah M Thursday, May 03, 2012 2:01 PM