Resource Cost update
-
Friday, April 13, 2012 9:13 PM
We are just in the process of setting up MS Project Server 2010. I discovered several of my resources did not have a standard or overtime cost set up - but I did not make the discovery until after they had timesheets entered and approved. Now I have a number of tasks that have hours applied, but show $0 cost. I have gone back and updated the resource costs. How do I get the task costs to update?
Thanks for the help,
Mike Ernst
All Replies
-
Friday, April 13, 2012 9:16 PM
All the applicable project plans need to be re-published to be able to view the costs in PWA.
In project professional, these should be calculated automatically when you open the plan.
Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com
- Proposed As Answer by Brian Kennemer, MVPMVP, Moderator Friday, April 13, 2012 10:57 PM
-