What field is used to populate the Resource Availabilty "Assignment Hours"?
-
Wednesday, April 11, 2012 2:50 PM
Project Server 2007 WSS
The problem I have is that the hours in this view (from the past) do not match the hours in the Resource Assignment view.
Resource Assignment shows (at least): Acutal work hours; Baseline Work hours; Work hours... etc
Resource Availability shows: Capacity; Availability; and "Assignment hours"... This number does not coorelate to any of the above numbers for completed work (in the past).
Please help me get to the bottom of this?
Cheers,
Thomas
All Replies
-
Friday, April 13, 2012 9:23 PM
Thomas,
As far as I know, the assignment hours should correlate to the "Work" at assignment level from the project plan.
Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com
-
Friday, April 13, 2012 11:20 PM
-
Sunday, April 15, 2012 2:30 AM
Prasanna & Reid,
Thank you very much for the answers. I assumed the same fields were being used, but had no direct way to verify the data call...
That said, perhaps I can ask for a little more of you assistance...
What would you do if the "Assignment" hours did not show the actual hours? What I mean is the actual hours are "committed", and those actual hours show up in the Resource Assignments view from PWA. Yet, they do not show up in the "Resource Availability" PWA view during the same time frame?
I am at a loss for the conclusion on how to fix this.
Thanks again,
Thomas
-
Monday, April 16, 2012 2:48 PM
Thomas,
It would be real helpful, if you can post some screen-shots of what you are seeing. May be the actual work got done during a different time than planned?
Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com