Proposed Answer Regarding Task publishing through PWA.

  • Wednesday, May 02, 2012 11:01 PM
     
     

    I have one question regarding Task publishing through PWA.

    if i publish the submitted hours from my team through PWA (Approve Center -> History), are the SPI and CPI automatically updated in the SSRS reports? or I need to manually publish my Work Plan again?

    We are using MSP 2010...

    I believe publishing through PWA also update the values to reports, but do SPI and CPI are also updated?

    thanks in advance.

    BR

    Irshad


    ...irshad

All Replies

  • Wednesday, May 02, 2012 11:41 PM
     
     Proposed Answer
     Hello Irshad,

    SPI and CPI values are calculated by scheduling engine used by Project Professional. PWA scheduling engine and Project Pro scheduling engine both are not identical

    When you publish a project plan via PWA, we call it as partial publishing and full publish when Project Professional is used.

    Hence you need to perform full publish to calculate these values.

    http://office.microsoft.com/en-us/project-help/spi-fields-HP001025917.aspx


    Hrishi Deshpande – DeltaBahn Senior Consultant
    Blog | < | LinkedIn

  • Thursday, May 03, 2012 5:19 PM
     
     
    Thanks Hrishi !