    Hello,

    I'm new to project server (just went live with a hosted instance) and am trying to make a change to a field in the "My Assignments" task view in PWA.  For some reason, duration is displaying in hours instead of days and I can't quite figure out how to change it.  Any thoughts would be appreciated.

All Replies

  • Wednesday, August 15, 2012 1:45 AM
     
     Proposed
    Ughhh... I just found the "Units" button in the toolbar which allowed me to make the change.  I thought it was something I'd have to change as an admin, didn't realize it was a user preference.