שאלה Custom job properties - lost when copying a job?

  • Monday, January 23, 2012 6:10 AM
     
     

    Hi all,

    I make extensive use of custom job properties to store application framework data. However, when I copy a job in the cluster manager (2008R2 SP2), the custom properties are not copied. Is this a bug or a feature? Am I doing something wrong?

    (It works well if I export the job to xml and then create a new job from the file. But that is just a workaround.)

    Regards

    Matthias

All Replies

  • Monday, January 23, 2012 4:39 PM
     
     

    Hi Matthias,

    Thank you for reporting this issue. It was reproduced and added to our bug database.

    Regards,
    Łukasz

  • Tuesday, October 16, 2012 10:32 AM
     
     

    Hi Lukasz,

    more than half a year has passed. Has this bug been fixed somehow?

    Regards

    Matthias

  • Tuesday, October 16, 2012 3:18 PM
     
     

    Hi Matthias,

    This issue is fixed in HPC Pack 2012 Beta: http://blogs.technet.com/b/windowshpc/archive/2012/09/06/announcing-the-hpc-pack-2012-beta-program.aspx

    Thanks,
    Łukasz

  • Wednesday, October 17, 2012 10:23 AM
     
     

    Hi Lukasz,

    thanks for the fast reply.

    Do I need to have Windows Server 2012 in order to run HPC Pack 2012?

    Regards

    Matthias

  • Wednesday, October 17, 2012 3:47 PM
     
     

    Hi Matthias,

    Yes, Windows Server 2012 is required on the headnode and WCF broker nodes.

    Regards,
    Łukasz