    Is it possible to show "status date" when working with timeline view?

Todas las respuestas

  • viernes, 15 de enero de 2010 16:06
    Moderador
     
     Respondida
    Hi Winson,

    Welcome to this Microsoft Project newsgroup :) As far as I know, there's no built-in way to do this. However, you could create a milestone (called it Status Date?)and show it on the Timeline. Double click on it and enter the Status Date you want. As Status Date defaults to 1700, I suggest you show the times as well on the timeline so you can synchronise the times.