Start and End dates for tasks are not displaying properly in Microsoft project
-
lundi 4 juin 2012 10:14
Hi,
I am trying to open Microsoft Project with an Xml file and the file content is as shown below.
<?xml version="1.0" encoding="utf-8" ?> - <Project xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xmlns:xsd="http://www.w3.org/2001/XMLSchema" xmlns="http://schemas.microsoft.com/project/2007"> <SaveVersion>12</SaveVersion> <UID>ADVP003</UID> <Title>Baseline Plan for ADVP003</Title> <Subject>Baseline Plan 1</Subject> <ScheduleFromStart>1</ScheduleFromStart> <StartDate>2012-01-02T08:00:00</StartDate> <FinishDate>2012-08-24T08:00:00</FinishDate> <CurrencyCode>$</CurrencyCode> <CalendarUID>1</CalendarUID> <DurationFormat>7</DurationFormat> <NewTasksEstimated>0</NewTasksEstimated> <Calendars /> - <Tasks> - <Task> <UID>1</UID> <ID>1</ID> <Name>COFFERDAM</Name> <IsNull>0</IsNull> <WBS>1</WBS> <OutlineNumber>1</OutlineNumber> <OutlineLevel>1</OutlineLevel> <Start>2012-01-02T08:00:00</Start> <Finish>2012-03-30T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>1</Summary> <Critical>0</Critical> <EarlyStart>2012-01-02T08:00:00</EarlyStart> <EarlyFinish>2012-03-30T17:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-01-02T08:00:00</ManualStart> <ManualFinish>2012-03-30T17:00:00</ManualFinish> </Task> - <Task> <UID>2</UID> <ID>2</ID> <Name>P1-Sheet Pile Cofferdam</Name> <IsNull>0</IsNull> <WBS>1.1</WBS> <OutlineNumber>1.1</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-01-02T08:00:00</Start> <Finish>2012-01-13T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-01-02T08:00:00</EarlyStart> <EarlyFinish>2012-01-13T17:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-01-02T08:00:00</ManualStart> <ManualFinish>2012-01-13T17:00:00</ManualFinish> </Task> - <Task> <UID>3</UID> <ID>3</ID> <Name>P3-Excavation Dredge Hole</Name> <IsNull>0</IsNull> <WBS>1.10</WBS> <OutlineNumber>1.10</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-03-05T11:00:00</Start> <Finish>2012-03-26T14:38:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-03-05T11:00:00</EarlyStart> <EarlyFinish>2012-03-26T14:38:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-02-27T05:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>25</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-03-05T11:00:00</ManualStart> <ManualFinish>2012-03-26T14:38:00</ManualFinish> </Task> - <Task> <UID>4</UID> <ID>4</ID> <Name>P1-Excavation Dredge Hole</Name> <IsNull>0</IsNull> <WBS>1.11</WBS> <OutlineNumber>1.11</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-03-01T08:00:00</Start> <Finish>2012-03-28T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-03-01T08:00:00</EarlyStart> <EarlyFinish>2012-03-28T17:00:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-02-22T02:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>10</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-03-01T08:00:00</ManualStart> <ManualFinish>2012-03-28T17:00:00</ManualFinish> </Task> - <Task> <UID>5</UID> <ID>5</ID> <Name>P2-Sheet Pile Cofferdam</Name> <IsNull>0</IsNull> <WBS>1.2</WBS> <OutlineNumber>1.2</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-01-04T08:00:00</Start> <Finish>2012-01-17T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-01-04T08:00:00</EarlyStart> <EarlyFinish>2012-01-17T17:00:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-01-04T02:30:00Z</ConstraintDate> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-01-04T08:00:00</ManualStart> <ManualFinish>2012-01-17T17:00:00</ManualFinish> </Task> - <Task> <UID>6</UID> <ID>6</ID> <Name>P3-Sheet Pile Cofferdam</Name> <IsNull>0</IsNull> <WBS>1.3</WBS> <OutlineNumber>1.3</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-01-06T08:00:00</Start> <Finish>2012-01-20T15:04:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-01-06T08:00:00</EarlyStart> <EarlyFinish>2012-01-20T15:04:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-01-06T02:30:00Z</ConstraintDate> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-01-06T08:00:00</ManualStart> <ManualFinish>2012-01-20T15:04:00</ManualFinish> </Task> - <Task> <UID>7</UID> <ID>7</ID> <Name>P1-Earthwork in Excavation upto Rock level</Name> <IsNull>0</IsNull> <WBS>1.4</WBS> <OutlineNumber>1.4</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-01-17T08:00:00</Start> <Finish>2012-01-30T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-01-17T08:00:00</EarlyStart> <EarlyFinish>2012-01-30T17:00:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-01-13T02:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>2</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-01-17T08:00:00</ManualStart> <ManualFinish>2012-01-30T17:00:00</ManualFinish> </Task> - <Task> <UID>8</UID> <ID>8</ID> <Name>P2-Earthwork in Excavation upto Rock level</Name> <IsNull>0</IsNull> <WBS>1.5</WBS> <OutlineNumber>1.5</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-01-19T08:00:00</Start> <Finish>2012-02-01T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-01-19T08:00:00</EarlyStart> <EarlyFinish>2012-02-01T17:00:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-01-17T02:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>5</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-01-19T08:00:00</ManualStart> <ManualFinish>2012-02-01T17:00:00</ManualFinish> </Task> - <Task> <UID>9</UID> <ID>9</ID> <Name>P3-Eartwork in Excavation upto Rock Level</Name> <IsNull>0</IsNull> <WBS>1.6</WBS> <OutlineNumber>1.6</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-01-23T15:04:00</Start> <Finish>2012-02-01T11:25:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-01-23T15:04:00</EarlyStart> <EarlyFinish>2012-02-01T11:25:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-01-20T09:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>6</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-01-23T15:04:00</ManualStart> <ManualFinish>2012-02-01T11:25:00</ManualFinish> </Task> - <Task> <UID>10</UID> <ID>10</ID> <Name>P1-Earthwork Excavation Through Hard Rock</Name> <IsNull>0</IsNull> <WBS>1.7</WBS> <OutlineNumber>1.7</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-02-01T08:00:00</Start> <Finish>2012-02-28T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-02-01T08:00:00</EarlyStart> <EarlyFinish>2012-02-28T17:00:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-01-30T02:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>7</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-02-01T08:00:00</ManualStart> <ManualFinish>2012-02-28T17:00:00</ManualFinish> </Task> - <Task> <UID>11</UID> <ID>11</ID> <Name>P2-Earthwork Excavation Through Hard Rock</Name> <IsNull>0</IsNull> <WBS>1.8</WBS> <OutlineNumber>1.8</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-02-03T08:00:00</Start> <Finish>2012-03-01T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-02-03T08:00:00</EarlyStart> <EarlyFinish>2012-03-01T17:00:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-02-02T02:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>8</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-02-03T08:00:00</ManualStart> <ManualFinish>2012-03-01T17:00:00</ManualFinish> </Task> - <Task> <UID>12</UID> <ID>12</ID> <Name>P2-Excavation Dredge Hole</Name> <IsNull>0</IsNull> <WBS>1.9</WBS> <OutlineNumber>1.9</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-03-05T08:00:00</Start> <Finish>2012-03-30T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-03-05T08:00:00</EarlyStart> <EarlyFinish>2012-03-30T17:00:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-02-24T02:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>11</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-03-05T08:00:00</ManualStart> <ManualFinish>2012-03-30T17:00:00</ManualFinish> </Task> - <Task> <UID>13</UID> <ID>13</ID> <Name>Concreting</Name> <IsNull>0</IsNull> <WBS>2</WBS> <OutlineNumber>2</OutlineNumber> <OutlineLevel>1</OutlineLevel> <Start>2012-02-03T11:00:00</Start> <Finish>2012-07-06T09:02:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>1</Summary> <Critical>0</Critical> <EarlyStart>2012-02-03T11:00:00</EarlyStart> <EarlyFinish>2012-07-06T09:02:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-02-03T11:00:00</ManualStart> <ManualFinish>2012-07-06T09:02:00</ManualFinish> </Task> - <Task> <UID>14</UID> <ID>14</ID> <Name>P1-Fabricating and placing Cutting Edge for well Foundation</Name> <IsNull>0</IsNull> <WBS>2.1</WBS> <OutlineNumber>2.1</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-03-30T08:00:00</Start> <Finish>2012-04-05T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-03-30T08:00:00</EarlyStart> <EarlyFinish>2012-04-05T17:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>4</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-03-30T08:00:00</ManualStart> <ManualFinish>2012-04-05T17:00:00</ManualFinish> </Task> - <Task> <UID>15</UID> <ID>15</ID> <Name>P3-Laying concrete in Bottom Plug,Top Plug</Name> <IsNull>0</IsNull> <WBS>2.10</WBS> <OutlineNumber>2.10</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-04-16T08:50:00</Start> <Finish>2012-05-03T08:02:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-04-16T08:50:00</EarlyStart> <EarlyFinish>2012-05-03T08:02:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>30</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-04-16T08:50:00</ManualStart> <ManualFinish>2012-05-03T08:02:00</ManualFinish> </Task> - <Task> <UID>16</UID> <ID>16</ID> <Name>P3-Drilling Hole with TMT anchor Bar</Name> <IsNull>0</IsNull> <WBS>2.11</WBS> <OutlineNumber>2.11</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-05-04T08:02:00</Start> <Finish>2012-05-21T15:40:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-05-04T08:02:00</EarlyStart> <EarlyFinish>2012-05-21T15:40:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>15</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-05-04T08:02:00</ManualStart> <ManualFinish>2012-05-21T15:40:00</ManualFinish> </Task> - <Task> <UID>17</UID> <ID>17</ID> <Name>P1-Drilling Hole with TMT anchor Bar</Name> <IsNull>0</IsNull> <WBS>2.12</WBS> <OutlineNumber>2.12</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-05-07T15:00:00</Start> <Finish>2012-05-24T10:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-05-07T15:00:00</EarlyStart> <EarlyFinish>2012-05-24T10:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>31</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-05-07T15:00:00</ManualStart> <ManualFinish>2012-05-24T10:00:00</ManualFinish> </Task> - <Task> <UID>18</UID> <ID>18</ID> <Name>P2-Drilling Hole with TMT anchor Bar</Name> <IsNull>0</IsNull> <WBS>2.13</WBS> <OutlineNumber>2.13</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-05-09T15:00:00</Start> <Finish>2012-05-28T10:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-05-09T15:00:00</EarlyStart> <EarlyFinish>2012-05-28T10:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>32</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-05-09T15:00:00</ManualStart> <ManualFinish>2012-05-28T10:00:00</ManualFinish> </Task> - <Task> <UID>19</UID> <ID>19</ID> <Name>P1-Laying Concrete</Name> <IsNull>0</IsNull> <WBS>2.14</WBS> <OutlineNumber>2.14</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-05-25T10:00:00</Start> <Finish>2012-06-06T09:31:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-05-25T10:00:00</EarlyStart> <EarlyFinish>2012-06-06T09:31:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>17</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-05-25T10:00:00</ManualStart> <ManualFinish>2012-06-06T09:31:00</ManualFinish> </Task> - <Task> <UID>20</UID> <ID>20</ID> <Name>P2-Laying Concrete</Name> <IsNull>0</IsNull> <WBS>2.15</WBS> <OutlineNumber>2.15</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-05-29T10:00:00</Start> <Finish>2012-06-07T09:02:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-05-29T10:00:00</EarlyStart> <EarlyFinish>2012-06-07T09:02:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>18</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-05-29T10:00:00</ManualStart> <ManualFinish>2012-06-07T09:02:00</ManualFinish> </Task> - <Task> <UID>21</UID> <ID>21</ID> <Name>P1-Cocreting in Bottom Plug under water condition</Name> <IsNull>0</IsNull> <WBS>2.16</WBS> <OutlineNumber>2.16</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-06-07T09:31:00</Start> <Finish>2012-07-05T09:31:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-06-07T09:31:00</EarlyStart> <EarlyFinish>2012-07-05T09:31:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>19</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-06-07T09:31:00</ManualStart> <ManualFinish>2012-07-05T09:31:00</ManualFinish> </Task> - <Task> <UID>22</UID> <ID>22</ID> <Name>P2-Cocreting in Bottom Plug under water condition</Name> <IsNull>0</IsNull> <WBS>2.17</WBS> <OutlineNumber>2.17</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-06-08T09:02:00</Start> <Finish>2012-07-06T09:02:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-06-08T09:02:00</EarlyStart> <EarlyFinish>2012-07-06T09:02:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>20</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-06-08T09:02:00</ManualStart> <ManualFinish>2012-07-06T09:02:00</ManualFinish> </Task> - <Task> <UID>23</UID> <ID>23</ID> <Name>P3-Cocreting in Bottom Plug under water condition</Name> <IsNull>0</IsNull> <WBS>2.18</WBS> <OutlineNumber>2.18</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-06-06T08:01:00</Start> <Finish>2012-06-28T13:01:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-06-06T08:01:00</EarlyStart> <EarlyFinish>2012-06-28T13:01:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>24</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-06-06T08:01:00</ManualStart> <ManualFinish>2012-06-28T13:01:00</ManualFinish> </Task> - <Task> <UID>24</UID> <ID>24</ID> <Name>P3-Laying Concrete</Name> <IsNull>0</IsNull> <WBS>2.19</WBS> <OutlineNumber>2.19</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-05-22T15:40:00</Start> <Finish>2012-06-05T08:01:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-05-22T15:40:00</EarlyStart> <EarlyFinish>2012-06-05T08:01:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>16</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-05-22T15:40:00</ManualStart> <ManualFinish>2012-06-05T08:01:00</ManualFinish> </Task> - <Task> <UID>25</UID> <ID>25</ID> <Name>P3-Earthwork Excavation Through Hard Rock</Name> <IsNull>0</IsNull> <WBS>2.2</WBS> <OutlineNumber>2.2</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-02-03T11:00:00</Start> <Finish>2012-03-02T11:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-02-03T11:00:00</EarlyStart> <EarlyFinish>2012-03-02T11:00:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-02-03T05:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>9</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-02-03T11:00:00</ManualStart> <ManualFinish>2012-03-02T11:00:00</ManualFinish> </Task> - <Task> <UID>26</UID> <ID>26</ID> <Name>P2-Fabricating and placing Cutting Edge for well Foundation</Name> <IsNull>0</IsNull> <WBS>2.3</WBS> <OutlineNumber>2.3</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-04-03T08:00:00</Start> <Finish>2012-04-09T17:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-04-03T08:00:00</EarlyStart> <EarlyFinish>2012-04-09T17:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>12</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-04-03T08:00:00</ManualStart> <ManualFinish>2012-04-09T17:00:00</ManualFinish> </Task> - <Task> <UID>27</UID> <ID>27</ID> <Name>P3-Fabricating and placing Cutting Edge for well Foundation</Name> <IsNull>0</IsNull> <WBS>2.4</WBS> <OutlineNumber>2.4</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-03-27T14:38:00</Start> <Finish>2012-04-03T14:38:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-03-27T14:38:00</EarlyStart> <EarlyFinish>2012-04-03T14:38:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>3</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-03-27T14:38:00</ManualStart> <ManualFinish>2012-04-03T14:38:00</ManualFinish> </Task> - <Task> <UID>28</UID> <ID>28</ID> <Name>P1- Filling Concrete in annular space between steel ring and well curb</Name> <IsNull>0</IsNull> <WBS>2.5</WBS> <OutlineNumber>2.5</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-04-09T08:00:00</Start> <Finish>2012-04-17T10:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-04-09T08:00:00</EarlyStart> <EarlyFinish>2012-04-17T10:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>14</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-04-09T08:00:00</ManualStart> <ManualFinish>2012-04-17T10:00:00</ManualFinish> </Task> - <Task> <UID>29</UID> <ID>29</ID> <Name>P2- Filling Concrete in annular space between steel ring and well curb</Name> <IsNull>0</IsNull> <WBS>2.6</WBS> <OutlineNumber>2.6</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-04-11T08:00:00</Start> <Finish>2012-04-19T10:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-04-11T08:00:00</EarlyStart> <EarlyFinish>2012-04-19T10:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>26</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-04-11T08:00:00</ManualStart> <ManualFinish>2012-04-19T10:00:00</ManualFinish> </Task> - <Task> <UID>30</UID> <ID>30</ID> <Name>P3- Filling Concrete in annular space between steel ring and well curb</Name> <IsNull>0</IsNull> <WBS>2.7</WBS> <OutlineNumber>2.7</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-04-04T14:38:00</Start> <Finish>2012-04-13T08:50:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-04-04T14:38:00</EarlyStart> <EarlyFinish>2012-04-13T08:50:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>27</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-04-04T14:38:00</ManualStart> <ManualFinish>2012-04-13T08:50:00</ManualFinish> </Task> - <Task> <UID>31</UID> <ID>31</ID> <Name>P1-Laying concrete in Bottom Plug,Top Plug</Name> <IsNull>0</IsNull> <WBS>2.8</WBS> <OutlineNumber>2.8</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-04-18T10:00:00</Start> <Finish>2012-05-04T15:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-04-18T10:00:00</EarlyStart> <EarlyFinish>2012-05-04T15:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>28</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-04-18T10:00:00</ManualStart> <ManualFinish>2012-05-04T15:00:00</ManualFinish> </Task> - <Task> <UID>32</UID> <ID>32</ID> <Name>P2-Laying concrete in Bottom Plug,Top Plug</Name> <IsNull>0</IsNull> <WBS>2.9</WBS> <OutlineNumber>2.9</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-04-20T10:00:00</Start> <Finish>2012-05-08T15:00:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-04-20T10:00:00</EarlyStart> <EarlyFinish>2012-05-08T15:00:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>29</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-04-20T10:00:00</ManualStart> <ManualFinish>2012-05-08T15:00:00</ManualFinish> </Task> - <Task> <UID>33</UID> <ID>33</ID> <Name>WELL STEINING</Name> <IsNull>0</IsNull> <WBS>3</WBS> <OutlineNumber>3</OutlineNumber> <OutlineLevel>1</OutlineLevel> <Start>2012-06-29T13:01:00</Start> <Finish>2012-08-24T16:12:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>1</Summary> <Critical>0</Critical> <EarlyStart>2012-06-29T13:01:00</EarlyStart> <EarlyFinish>2012-08-24T16:12:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-06-29T13:01:00</ManualStart> <ManualFinish>2012-08-24T16:12:00</ManualFinish> </Task> - <Task> <UID>34</UID> <ID>34</ID> <Name>P1-Concreting in Well cap and Tie Beam below substructure</Name> <IsNull>0</IsNull> <WBS>3.1</WBS> <OutlineNumber>3.1</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-07-06T09:31:00</Start> <Finish>2012-07-30T15:52:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-07-06T09:31:00</EarlyStart> <EarlyFinish>2012-07-30T15:52:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>21</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-07-06T09:31:00</ManualStart> <ManualFinish>2012-07-30T15:52:00</ManualFinish> </Task> - <Task> <UID>35</UID> <ID>35</ID> <Name>P2-Concreting in Well cap and Tie Beam below substructure</Name> <IsNull>0</IsNull> <WBS>3.2</WBS> <OutlineNumber>3.2</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-07-09T09:02:00</Start> <Finish>2012-07-31T15:23:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-07-09T09:02:00</EarlyStart> <EarlyFinish>2012-07-31T15:23:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>22</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-07-09T09:02:00</ManualStart> <ManualFinish>2012-07-31T15:23:00</ManualFinish> </Task> - <Task> <UID>36</UID> <ID>36</ID> <Name>P3-Concreting in Well cap and Tie Beam below substructure</Name> <IsNull>0</IsNull> <WBS>3.3</WBS> <OutlineNumber>3.3</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-06-29T13:01:00</Start> <Finish>2012-07-30T09:51:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-06-29T13:01:00</EarlyStart> <EarlyFinish>2012-07-30T09:51:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>23</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-06-29T13:01:00</ManualStart> <ManualFinish>2012-07-30T09:51:00</ManualFinish> </Task> - <Task> <UID>37</UID> <ID>37</ID> <Name>P1-Concreting in Well Curb</Name> <IsNull>0</IsNull> <WBS>3.4</WBS> <OutlineNumber>3.4</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-07-31T15:52:00</Start> <Finish>2012-08-23T13:13:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-07-31T15:52:00</EarlyStart> <EarlyFinish>2012-08-23T13:13:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>34</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-07-31T15:52:00</ManualStart> <ManualFinish>2012-08-23T13:13:00</ManualFinish> </Task> - <Task> <UID>38</UID> <ID>38</ID> <Name>P2-Concreting in Well Curb</Name> <IsNull>0</IsNull> <WBS>3.5</WBS> <OutlineNumber>3.5</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-08-01T15:23:00</Start> <Finish>2012-08-24T11:44:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>0</Critical> <EarlyStart>2012-08-01T15:23:00</EarlyStart> <EarlyFinish>2012-08-24T11:44:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-06-21T10:30:00Z</ConstraintDate> - <PredecessorLink> <PredecessorUID>35</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-08-01T15:23:00</ManualStart> <ManualFinish>2012-08-24T11:44:00</ManualFinish> </Task> - <Task> <UID>39</UID> <ID>39</ID> <Name>P3-Concreting in Well Curb</Name> <IsNull>0</IsNull> <WBS>3.6</WBS> <OutlineNumber>3.6</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-07-31T09:51:00</Start> <Finish>2012-08-24T16:12:00</Finish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-07-31T09:51:00</EarlyStart> <EarlyFinish>2012-08-24T16:12:00</EarlyFinish> <ConstraintType>0</ConstraintType> <CalendarUID>-1</CalendarUID> - <PredecessorLink> <PredecessorUID>36</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> <ManualStart>2012-07-31T09:51:00</ManualStart> <ManualFinish>2012-08-24T16:12:00</ManualFinish> </Task> </Tasks> </Project>
In the above Xml code block i have defined Project information, Tasks and its predecessor links.
After opening Project with an Xml file , The start and end dates of project and tasks are not displaying
as which are in Xml file.
For example consider the above Xml code block
there Project start and end dates are "2012-01-02T08:00:00" and "2012-08-24T08:00:00" respectively
but these are not displaying as it is.
The task "COFFERDAM" is a summary task and its start and end dates are "2012-01-02T08:00:00" and
"2012-03-30T17:00:00" respectively, it has a sub tasks "P1-Sheet Pile Cofferdam" is a successor to
"P1-Earthwork in Excavation upto Rock level ", "P2-Sheet Pile Cofferdam" is a successor to
"P2-Earthwork in Excavation upto Rock level" and "P3-Sheet Pile Cofferdam" is a successor to
"P3-Eartwork in Excavation upto Rock Level".... , Like this i have defined data . My problem is
the start and end dates for all the tasks are not displaying properly in Microsoft project as the dates
i have defined in Xml file. Please suggest me what is the problem?
- Déplacé Sapna Shukla - Project MVPMVP, Moderator lundi 4 juin 2012 12:29 (From:Project Standard and Professional General Questions and Answers)
Toutes les réponses
-
lundi 4 juin 2012 11:15Modérateur
Hi,
Presentation of dates (and time of day) in MS Project is governed by the Options. In Project 2010 (I guess because you did not mention your version) click File, then Options, and in the Genral pad select the date format you want.
Greetings,
-
mercredi 6 juin 2012 11:48
Hi Jan,
<Task> <UID>3</UID> <ID>3</ID> <Name>P3-Excavation Dredge Hole</Name> <IsNull>0</IsNull> <WBS>1.10</WBS> <OutlineNumber>1.10</OutlineNumber> <OutlineLevel>2</OutlineLevel> <Start>2012-03-05T11:00:00</Start> <Finish>2012-03-26T14:38:00</Finish> <ManualStart>2012-03-05T11:00:00</ManualStart> <ManualFinish>2012-03-26T14:38:00</ManualFinish> <Estimated>0</Estimated> <Milestone>0</Milestone> <Summary>0</Summary> <Critical>1</Critical> <EarlyStart>2012-03-05T11:00:00</EarlyStart> <EarlyFinish>2012-03-26T14:38:00</EarlyFinish> <ConstraintType>4</ConstraintType> <CalendarUID>-1</CalendarUID> <ConstraintDate>2012-02-27T11:00:00</ConstraintDate> - <PredecessorLink> <PredecessorUID>25</PredecessorUID> <Type>1</Type> <CrossProject>0</CrossProject> <LinkLag>1</LinkLag> <LagFormat>7</LagFormat> </PredecessorLink> <Active>1</Active> <Manual>0</Manual> </Task>
I the above Xml content please observe <PredecessorLink> part, there i have defined LagFormat as "Day" and
LinkLag is "1" (1 Day).When i open this XML with microsoft project (MPP), for the task "P3-Excavation Drdge Hole"
is displaying properly but its Predecessors column showing as "25FS+0 days" , there LinkLag is
showing as 0 day but i mentioned it as "1 Day" in my Xml content.
In MPP i have made LinkLag as "1 Day" and generated saved it to Xml file, In that Xml file i am seeing below
code
<PredecessorLink><<PredecessorUID>25</PredecessorUID><Type>1</Type><CrossProject>0</CrossProject><LinkLag>4800</LinkLag><LagFormat>7</LagFormat></PredecessorLink>In the above Xml contents i am showing only Predecessors part.
There instead of "1 day" LinkLag value showing as "4800", What is this "4800" and How to calculate?
-
mercredi 6 juin 2012 13:27Modérateur
Hi,
First, I don't read any XML, but the objects seem very similar to what I know from VBA.
The fact that you define "Day" as the format for duration and lag only means that that's how they will be DISPLAYED and used in the visual part.. In VBA (and I suspect in XML as well) values of the both must be entered in minutes. You probably have [Hours per Day] in the options set as 8, so there are 4800 minutes in a day. Note that there is a constant [Minutes per Day] that you can use as more general than 4800.
This also explains that 1 is rounded to 0 since translating 1 minute into days gives something like 0,0003 days and Project only keeps 2 decimals.
Hope this helps,