Protected Baselines - not foolproof??
-
lundi 6 septembre 2010 18:50
With Protected Baselines enforced I cannot (eg as a PM) set or clear Baselines 6-10..which is great..but it appears only to work when attempted from the Set/Clear dialog box in Project Professional. If I add the column Baseline Finish 6 into my table I find that I can amend, save and publish changes. Have I missed something here or is stopping PMs from not altering certain snapshots of dates not possible? Thanks in advance.
Toutes les réponses
-
mardi 7 septembre 2010 00:25Modérateur
I hope the following article will give good picture:
http://technet.microsoft.com/en-us/library/cc197622.aspx
Save Protected Baseline:
Allows a user to save a protected baseline or clear a protected baseline associated with an enterprise project published to the Project Server database. Grant this permission to project managers who have to save baselines in their projects. Baselines are saved by using the Set Baseline functionality accessed from the Project Professional ribbon on the Project tab in the Schedule group. Click the Set Baseline button and then select Save Baseline or Clear Baseline. Protected Baselines are in the range of Baseline 0-5 inclusive. Only users who have Save Unprotected Baseline, Open Project and Save Project Category permissions are able to save Baselines in Baseline 6-10.
Cheers. Happy troubleshooting !!! Sriram E - MSFT Enterprise Project Management- Proposé comme réponse Christophe FiessingerMicrosoft Employee, Owner mardi 7 septembre 2010 02:43
- Marqué comme réponse Alexander Burton [MVP]MVP, Moderator samedi 11 juin 2011 22:44
- Non marqué comme réponse Stev Scott42 mardi 16 avril 2013 19:14
-
mardi 7 septembre 2010 17:05Hi, sorry this doesn't solve the issue. Even with the above permission in force, I can still manually edit the dates in any of the Baselines 6-10 and the changes are saved..so it looks like the permission does not fully lock down the data??