Proj 10 Visual Cash Flow Report by FY
-
יום רביעי 25 אפריל 2012 19:06Can I somehow make the visual flow cash report to represent the numbers in FY?
כל התגובות
-
יום רביעי 25 אפריל 2012 19:44
plclem,
As far as I know, the "somehow" will require either copy and paste from the Resource Usage view (set to show fiscal years) or a macro that exports the data exactly as you want/need it.
John
-
יום שני 30 אפריל 2012 10:05מנחה דיון
You can refer to the given link for some ground work : http://office.microsoft.com/en-us/project-help/produce-a-visual-report-of-project-2007-data-in-excel-HA010235237.aspx
http://office.microsoft.com/en-us/project-help/create-a-visual-report-HA010163709.aspx
Sapna S