Filter problem in Project Center View
-
2012. január 10. 15:30
Hi,
I have a problem with one view with filter in PS2010 Project Center page.
I created one view on project Center and when I apply filter in that view I recived error "An unknown error has occurred" on Project Center page
I use one custome field with lookup table, as a criteria ("ProjectType - equals - Implementation")
When I remove that filter from view, the view works fine. All other views (without filter) works fine all time.
Any ideas or solutions?
Az összes válasz
-
2012. január 11. 10:17
Hi,
Project Type can only be
Project,
Master Project
Global
ResGlobal and so on.
I tried it and didn't notice you're using project type :) I think you mistakenly selected project type. Just check and correct it.
Thanks,
Kashif
-
2012. január 12. 13:51
Hi
Little correction!
I put ("ProjectType - equals - Implementation") as an example.
We don’t use default Project Type filed from PS, but we create custom enterprise field with name "ASProjectType", and that field has lookup table with same name and in that lookup table we have few options: Internal, Implementation, Maintenance etc.
When I create filter on that view, PS verified that filter is OK (with green tick), and allow me to save that view. However, when I try load that view in Project Center I receive "An unknown error has occurred" error.
When I remove that filter from view, the view works fine.
-
2012. január 13. 7:23
Hi,
Did you try looking into the ULS and/or event viewer?
Thanks, Kashif -
2012. január 23. 15:34
Hi,
I look in there but I didn't find anything useful. (it was just quck look :( )
If you have some hint what to look for or any other ideas?
-
2012. április 17. 13:40
We have exactly the same problem. Any solutions for this.
We noticed also that this happens occurs after installing latest CU (from March 7th). So this means this is not fixed yet?
-
2012. április 18. 16:16
Hi ,
i guess you will find the solution in this update
http://support.microsoft.com/kb/2598251
and the full description by Brian Smith is below
http://blogs.msdn.com/b/brismith/archive/2012/04/16/project-server-2010-an-unknown-error-in-project-center-usually-related-to-filters-and-duplicate-custom-field-values.aspx
cheers
Malek AlShayeb