Can Project Server auto-level
-
2012. május 2. 15:08
Can I configure PS2010 to not allow a resource to be assigned to a project task if that resource is already assigned elsewhere infor another project that same period of time? This is to answer repeated questions I get from potential clients in relation to the solution performing the role of "resource manager" instead of a human in smaller organisations.
thanks in advance.
Az összes válasz
-
2012. május 2. 17:36Moderátor
Stev Scott42 --The answer to your question is no; you cannot prevent PMs from assigning resources to tasks if the resource is already assigned to tasks during the same time period in other projects. Hope this helps.Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"- Megjelölte válaszként: Stev Scott42 2012. május 2. 19:31
-
2012. május 2. 19:31
thanks Dale, I thought so but just wanted to be sure. I will therefore continue to bang the "you need a process" drum rather than expect a solution that makes decisions automatically.
cheers
Steve
-
2012. május 2. 20:57ModerátorSteve --Yup, bang that drum, my friend! This is one of many issues with Project Server 2010 that are best addressed with a standardized methodology or process. And you are more than welcome for the help, my friend! :)
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"