Timesheet Issue
-
2012. február 28. 14:37
hi ,
1.when i click " create new timesheet" ,new timesheet shows up with default hours like .5 h for friday .how to slove this issue ?
2.If i enter actual hours as below in a timesheet
mon tue wed thu fri
6h 6h 6h 6h 6h
after submitting timesheet , it changes to
mon tue wed thu fri
6.47h 6h 6h 6h 6.07h
please help me reslove this .- Szerkesztette: PriyaDarshini_t 2012. február 28. 15:10
Az összes válasz
-
2012. február 28. 15:20Moderátor
Hi,
in recent cumulative updates, some issue like that had been resolved. Especially in CU Oct and Dec. They are mainly related to Single entry mode. Have you SEM enabled? If so, I suggest to apply recent CU to avoid this issue in future.
But test first on a test environment, since there was a major change regarding SEM in CU Dec11. Updates in Tasks will not be reflected automatically in Timesheets. Changes in Timesheets will still be poulated to Tasks. You can also have a look at webcast. For more information, have a look at http://blogs.technet.com/b/projectadministration/archive/2011/12/14/microsoft-project-server-and-sharepoint-server-2007-and-2010-december-2011-cu-announcement.aspx.
Regards
Barbara