Is it possible to represent BCWS in hours?

Traitée Is it possible to represent BCWS in hours?

  • 2010. augusztus 26. 15:31
     
     

    Our PMO wants to have two views for EV.  One is pretty standard.  It just shows all the built-in EV fields, (BCWP, BCWS, SV, etc...).  Everything represented in dollars.  However, they want a second view with those values represented in hours.  It's an odd request, and I can't really find any examples of others doing this, so I suspect it's not very common.

Az összes válasz

  • 2010. augusztus 27. 3:16
     
     

    Hi Kevin,

    If you assume the resource standard rate is $1, EV values are same for hours and cost.

    Example:

    BCWP = % complete * (Planned Hours till status date * Rate) 

    If standard rate for resource is $1, so BCWP as below:

    BCWP = % complete * (Planned Hours till status date * 1) 

    Thanks
    Chak

     


    Chak Tukkadi pVector Technologies Consulting: http://www.pvectortech.com Blog: http://www.epmcentral.com
  • 2010. augusztus 27. 7:38
    Moderátor
     
     
    You can use rate B for teh $1 rate and swap as required
    The one and only Project VBA Book Rod Gill Project Management
  • 2010. augusztus 27. 16:16
     
     
    Thanks Chak, but what if I have different rates for different resources?  Do I have access to that data in a custom field?
  • 2010. augusztus 27. 16:25
    Moderátor
     
     Válasz
    You could do it in Excel....export timephased Baseline Work & Actual Work
    to Excel into a table. Then calculate Cumulative Work and Cumulative Actual
    Work within Excel.
     
    BCWS => Cumulative Baseline Work
    BCWP => % Work Complete X Baseline Work
    ACWP => Cumulative Actual Work
     
    ....or something like that.
     
    - Andrew Lavinsky