Project 2007: Milestones converted into activities after users report on progress in PWA. How to avoid it?
-
2010. augusztus 26. 7:05
Subj.
Each milestone has human resource (PWA user) assigned to it, so that he can report on progress.
After PWA user set new dates for milestone, lets say he changes its start date, this milestone become activity.
How to avoid it?
Az összes válasz
-
2010. augusztus 26. 13:38
Hi Valery,
I have seen this problem, if the Milestone is planned with zero duration. To avoid this plan the Milestone with some duration and mark it as Miswstone.
Regards, Sujit - MSTC- Válasznak javasolta: Avinash kr 2010. augusztus 27. 9:00
-
2010. augusztus 27. 8:08
Setting non-zero duration does not work.
But I've found solution - you should set work type "Fixed-Unit" or "Fixed-Work", in this case milestones will remain milestones with zero duration.
- Megjelölte válaszként: Valery Baranov 2010. augusztus 27. 8:08