Are Barstyles Views specific?
-
24 September 2010 13:13
Hi,
Are Barstyles Views specific? if yes, how can i get the bar styles from one view to other view?
Semua Balasan
-
24 September 2010 13:29Moderator
Hi Ram,
Yes, barstyles are view specific.
But I don't know of any way to copy basrstyles from one view to another. You can copy a view though and modify the new view. Barstyles are also copied when you copy a view.
I hope this helps,
Hans
My EPM blog: Projectopolis- Ditandai sebagai Jawaban oleh ram kanumuri 24 September 2010 13:56
-
24 September 2010 13:57Thanks HansH.
-
26 September 2010 23:42
Hi Ram
A trick that I used prior to 2010 was using the View Tables menu :-
Set up tables for each of your views, with different coumns, eg Tracking, cost etc
Then set the barstyles that you want
save the view by view more views, copy as your new name
then change your table by View Table More tables choose the table
the Barstyle shoudl stay the same
then view more views, copy and you then have the common bar styles with a different set of table columns
Not usre if you van do this in Proejct 2010, it seems that Microsoft have forgotten the long time users agian and forcing us to learn a whol new interface , the ribbon !! which takes up valuable screen space compared to a simple menu line
good luck
hope this helps
regards
Tom Hadley
Senior consultant
The Project Management Workshop
over 20 years experience with using and training in Project
- Disarankan sebagai Jawaban oleh Tom in the gong 26 September 2010 23:42