I am trying to dynamically link a milestone from a subproject into the master project area. I have done about 30 links so far but now MSP 2010 is copyingthe milestone with a duration that totals the whole activity (ie 131 days).
I can't change it back to zero duration as it breaks the link.
I have tried to delete it and re-create the link but it doesnt fix it.
Has anyone seen this error before and how do I fix it.
I have 9 projects to link milestones from so have only just started.