Visual Report keeps crashing...how do I get the timephased info out?
-
06 Juni 2012 20:34
Hi all...I have also posted this on www.mpug.com and have had some discussions on this topic in an older thread on this forum but still having issues so I am reposting as a new issue.
I'm using Project Pro (SP1 & Cumulative patches installed; both Office and Project 'repaired' after it was a suggested fix) and am trying to pull the Resource Availability Visual Report into excel.
I am using a Resource Pool with only 50 resources with about 6 plans connected to it. I also have a Master file created with all the .mpp files inserted as a sub-project. I have taken these files off the network and currently have them on a USB stick and access them via a laptop.
ISSUE #1
I get the following error FROM EXCEL:
File system error: An error occurred while opening 'D:\DOCUME~1\PKMACCT\Locals~1\Temp\1\Visual Reports Temporary Data\{acdeafd6-f32c-4192-8d9e-b5ca6ac126a8}\ResourceTP.cub'local cube file
All other reports can be created, though they are based on a 2003 template.
I have tried replacing the 2003 template for this report with a 2010 version of the file, but my system simply recreated it and the report still pulls the .xlt file, not the new one.
ISSUE #2
In a desperate attempt to get something to work, I disconnected each plan from the Resource Pool and used the Master to create this report and it worked!
Only problem is I now have duplicate entries for Resources assigned to multiple projects and cannot filter on projects. (I tried a custom field to bring the project names over but all it would return is a NULL value)
I've also noticed this report is basing availability off of Max Units. This is an issue, since I schedule with 100% (or more when it's a group) Max Units and have a modified Base Calendar. Is there any quick fix to this?
Thanks in advance for any and all help provided!
Shelley
Shelleyb