Retain Manually Set Cell Background Colors In Multiple Views
-
04 Juni 2012 19:16
I have specific cells within MS Project 2007 with a background color set to something other than "Automatic." When I switch Views the background colors disappear. It seems that manually set cell colors are only valid for the View in which is was created. Is there a way to make these formatting changes applicable to more than just the one View? Thanks!
- Diedit oleh WayNerd1 04 Juni 2012 19:16
Semua Balasan
-
04 Juni 2012 19:48
WayNerd1,
Sorry no. Custom formatting is unique to the view. You could use VBA to run a macro that would set cell formatting for different views but that's the only method I know.
John
- Disarankan sebagai Jawaban oleh Project User 05 Juni 2012 4:10
- Ditandai sebagai Jawaban oleh Jan De Messemaeker - Project MVPMVP, Moderator 05 Juni 2012 7:24
-
04 Juni 2012 20:27Thanks John. Not what I wanted to hear, but at least now I'm not searching for something that doesn't exist. :)
-
05 Juni 2012 1:19
WayNerd1,
You're welcome. If you feel your question was answered please mark it so.
John