Project Server 2010 Timesheet doesn't display planned work

Proposed Answer Project Server 2010 Timesheet doesn't display planned work

  • 11 April 2012 14:10
     
     

    I have a problem, that Timesheets are not updated with the Planned work, if the task is added or changed after the Timesheet is created. Is there a way to update planned work in Timesheet in this situation?

    Steps to reproduce:

    1. Project with task1 is created with work amount 1 day.

    2. Create timesheet for that period.

    3. Project is updated that task1 work amount is 2 days. And task2 with work amount 3 days is added.

    => As a result in Timesheet for task1 still planned work amount is 1 day. And there is task2, but without planned work.

    I have found out, that I can update planned work by deleting and re-creating timesheet. Is there some better way?

Semua Balasan

  • 11 April 2012 14:26
     
     Saran Jawaban

    Hi, Joseley.  This will be a thread to watch.  I'll assume you are using MSProject 2010 Enterprise.  One solution, perhaps not perferred, is to have the user delete their timesheet then re-create it.  Make sure they do the dump to Excel first and have them check any entries they made, particularly on any Administrative categories which can sometimes get lost in timesheet deletions.

    Alan

    QBE North America

    608-825-5073