Project Professional 2010 and Project Server 2010/ custom fields > graphical indicators with custom GIFs?
-
14 Mei 2012 17:52
Dear Forum,
i've a short question: is it possible to enhance Project Professional und Project Server with an enlarged custom set of icons (GIFs?) to use as graphical indicators. If it's possible, how can it be done?
Background: a customer would like to use throughout their reports a custom set of intuitive and well known graphical indicators.
Thank you for your hints and best regards
Philipp
- Diedit oleh PhilippH 14 Mei 2012 18:07
Semua Balasan
-
14 Mei 2012 18:33
Hi Philipp,
The icons that you see in PWA are on the file system in the 14 hive directory but I dont think it would be supported to change these. I dont think would be possible to update the Project Pro icons, and again, if you could it wouldn't be supported to do so.
Thanks
Paul
Paul Mather | Twitter | http://pwmather.wordpress.com
- Ditandai sebagai Jawaban oleh Christophe FiessingerMicrosoft Employee, Owner 14 Mei 2012 19:14
-
14 Mei 2012 18:38
Thank you Paul,
that is a quick answer. Seems like changing the icons would go under "hacking", so we'll be fine with the existing icons.
Best regards
Philipp
-
14 Mei 2012 18:41
No problem, glad to help (even though it wasnt the answer you were looking for!)
Thanks
Paul
Paul Mather | Twitter | http://pwmather.wordpress.com
-
14 Mei 2012 19:17
Hi Philipp,
In addition to Paul's sound advice, changing graphical indicators are not supported. Icon size has been hard coded to specific size and dimension.
Image files from 14 hive directory are linked with various DLL files; hence not supported to modify the out of the box graphical indicators
Hrishi Deshpande – DeltaBahn Senior Consultant
Blog | < | LinkedIn
- Diedit oleh Hrishi.Deshpande 14 Mei 2012 19:18 correction